Nebius puts the neocloud playbook to the test with $40 billion in planned spending

Business 0 views

Nebius plans $40 billion for AI capacity, but Microsoft Vineland delays and third-party problems expose financing risks in customer-funded buildouts.

Key Takeaways

  • Nebius plans $40 billion in 2027 AI infrastructure spending, relying heavily on customer prepayments and contract-backed debt.
  • Microsoft’s delayed Vineland, New Jersey data center highlights the financing risk: late delivery can strain Nebius’ balance sheet and cash flow.
  • The Microsoft contract, worth up to $19.4 billion, now has part of its capacity slipping into Q2 2027, with termination rights and penalties if deadlines are missed.
  • Nebius blames third-party operator DataOne for the delay, while Microsoft is tightening oversight of neocloud and third-party data center projects.
  • Despite delays, Nebius says its self-built sites are on track and forecasts $12–13 billion in 2027 revenue, but it cut its 2026 outlook and its shares fell.

Nebius sets $40 billion 2027 spend amid Microsoft Vineland delays

Meta description: Nebius plans $40 billion for 2027 AI capacity, but Microsoft’s Vineland data center delay exposes financing risks in third-party buildouts overall.

Tags: Nebius, Microsoft, AI data centers, Vineland, capital expenditure

Featured image: Abstract AI data center network, blue and green tones, no people, logos or text.

Nebius told investors Thursday on its third-quarter earnings call that it plans $40 billion in spending for 2027, a figure far above Wall Street expectations. The plan is ambitious, and it rests on a string of projects that are already starting to show cracks. The larger risk is not the ambition alone, but the financing structure behind it: Nebius intends to use customer prepayments and loans backed by customer contracts to fund data centers, making delivery schedules at sites such as the Vineland, New Jersey, Microsoft capacity project central to its balance sheet.

Background: A buildout financed by customers

Nebius said it will fund the 2027 buildout by relying on customer prepayments and debt tied to signed contracts, effectively using the future value of data centers to pay for construction. That approach can work if capacity arrives on time, but it becomes risky when projects are delayed or canceled. CEO Arkady Volozh acknowledged the pressure during the call: “Building at this scale is hard, and delays are part of our industry right now,” he said. “We are not immune.”

The timing of the announcement also follows reports that Microsoft is becoming more cautious about neocloud deals that fail to meet delivery dates. For Nebius, whose financing increasingly depends on customer payments, a late site can mean continued spending on infrastructure while expected revenue arrives later than planned.

Development: Vineland timing slips under third-party control

One of Nebius’ largest customers, Microsoft, is paying for AI computing capacity at a Vineland, New Jersey, data center that is now months behind schedule. The contract is worth up to $19.4 billion, but delivery dates have already moved. Nebius now expects only just over half of the Microsoft capacity to be delivered by the end of the year, with the remaining tranche scheduled for the second quarter of 2027.

The original deployment window was 2025 and 2026, so the second quarter of 2027 sits well outside that timeline. Nebius summarized the contract terms as giving Microsoft the right to terminate affected service after a grace period if delivery dates are missed and no alternative capacity is offered. The agreement also contains financial penalties for late delivery.

Nebius attributes the Vineland delay to DataOne, the third-party operator of the site. Andrey Korolenko, Nebius’ chief product and infrastructure officer, said DataOne “decided to wind down the temporary generation faster than it was expected,” as the site transitions to Bloom Energy fuel cells. The transition was not entirely by choice. In August, the investigative site Floodlight reported that at least 45 natural gas generators were operating at the DataOne site without permits for gas generation. New Jersey regulators fined the facility $1.1 million, finding that the generators violated federal law. DataOne is separately facing a noise-complaint lawsuit from nearby residents over a constant humming noise allegedly emitted by the data center.

Nebius said Microsoft “has been part of the planning process,” but did not say whether Microsoft has agreed to the new dates. Microsoft has not publicly canceled anything. TechCrunch has reached out to Nebius, Microsoft and DataOne for comment.

Latest: Microsoft oversight and Nebius financial outlook

Marc Boroditsky, Nebius’ chief revenue officer, said the company’s Microsoft and Meta contracts both came with significant prepayments that arrived long before delivery. But Bloomberg reported last week that Microsoft is tightening oversight of third-party projects, including those run by Nebius, IREN and Nscale, and is debating whether to sign new agreements. Bloomberg also reported that Microsoft sent employees to the New Jersey site.

Microsoft’s own quarterly earnings report noted that its capital expenditure was lower than expected because of third-party delays. Bloomberg reported that Microsoft will not use an option to more than double its Nscale agreement for a Texas data center and recently stopped being an anchor customer for Nscale’s planned Essex site after power delays.

Nebius says the delays it faces are coming from sites it does not control, while data centers it is building itself are coming online on time or ahead of schedule. Those self-built sites are expected to supply most of its new capacity from 2027. Boroditsky said new deals signed in the third quarter included prepayments that more than cover the cost of building the capacity behind them. Nebius ended the quarter with $7.4 billion in cash.

The company expects total prepayments plus asset-backed financing tied to investment-grade contracts to cover up to 85% of a $40 to $45 billion 2027 capital expenditure plan. CFO Maria Del Dado Alonso Sanchez named Microsoft and Meta as contracts that can be financed in that way, and Boroditsky said Nebius could “tap prepayments to shore up any additional cash requirements.”

For revenue, Nebius forecast $12 to $13 billion in 2027 and said it expects to break even on a pre-tax basis by the fourth quarter. In the third quarter, Nebius reported revenue of $981 million, up 571% from a year earlier, with roughly a third coming from a one-time payment tied to a new partnership model. It cut its 2026 revenue forecast by $200 million to $3 billion, citing delays at third-party sites including New Jersey. Shares ended the day down 17%.

Current stage: financing depends on on-time delivery

Nebius is now at a point where its 2027 buildout plan depends on two separate engines: self-built capacity that it says is on schedule, and customer-funded third-party projects that are already showing timing strain. The next signals to watch are whether Microsoft accepts the revised Vineland dates, whether DataOne completes the Bloom Energy transition without further penalties or litigation, and whether prepayments remain sufficient to cover the $40 to $45 billion spending plan if delivery slips again.

Tags: MicrosoftAI data centerscapital expenditureNebiusVineland