Public opposition to data centers may actually be about electricity.
Virginia's AI data center backlash reflects grid costs, fossil-fuel power, air pollution and transmission rules as OpenAI and Anthropic expand.
Key Takeaways
- Public backlash against data centers is driven less by abstract anti-tech sentiment than by concrete electricity issues: grid capacity, rising costs, air pollution, and local environmental impacts.
- AI data centers require enormous power, often hundreds to thousands of megawatts, putting new strain on existing grids and pushing regulators to require developers to pay for transmission upgrades and accept possible curtailment during peak demand.
- Many new AI facilities are bypassing public utilities by installing onsite natural gas turbines and diesel backup generators, as seen in Anthropic’s reported $3.4 billion turbine purchase.
- Because electricity availability—not just opposition—is the key constraint, developers may shift to low-population areas like the Permian Basin or to overseas locations such as Malaysia where power can be secured with fewer objections.
Meta Description: Data center backlash in Virginia turns on electricity, grid costs and air pollution as OpenAI and Anthropic expand AI infrastructure and seek new power sources.
Tags: data center backlash, AI infrastructure, electricity grid, OpenAI, Anthropic
Featured Image: Abstract illustration of a grid-connected data center powered by gas turbines and diesel generators, no people, no company logos, no text.
Background: A Virginia Neighborhood Becomes the Map
Last week, while voters went to the polls across the US, Ashburn, Virginia, part of Data Center Alley, was already a visible center of the argument about AI’s physical footprint. Data Center Alley is described as the world’s largest data center hub, and concrete buildings for Skybox and CloudHQ line major roads, making the region a practical test case for the broader data center backlash. The account first appeared in The Algorithm, a weekly newsletter on AI.
The debate often starts with culture. Chris Lehane, chief global affairs officer at OpenAI, wrote two days after the midterms that data centers had become a proxy for public unease about affordability, corporate power and people losing control over their futures. But Elena Schlossberg, a prominent Virginia activist against data centers, said the fight had always been about electricity. Some Virginia protesters appear more animated by broader anti-tech populism, but the particular consequences of drawing so much power from the grid have shaped how the backlash has played out.
Development: Grid Limits Turn Protest Into Rules
Most data centers in this part of Virginia connect to the existing grid. Inside one Equinix facility, onsite diesel generators provide backup, while routine power comes from Dominion Energy, a local utility whose generation mix includes a large share of natural gas, cleaner than coal or oil but worse than renewables. The average data center operating there today has a power capacity of 54 megawatts, more than the power draw of Denver International Airport.
That capacity is small compared with the ambitions now spreading across the country. The smallest AI data centers attractive for training use 300 megawatts, and one developer said he is eyeing a former steel mill already equipped to draw that much electricity from the grid. Ideal facilities are closer to 6,000 megawatts, the estimated draw of the city of Chicago. Chicago is powered by more than 20 power plants within the city alone, plus dozens farther out.
Recent protests pushed Virginia state rules toward a new baseline: data centers must pay fully for the cost of new transmission lines to the grid, so those costs are not spread among everyone else. Developers said they are preparing for rules that could cut them off from grid power during peak demand. Schlossberg warned that a strained grid could lead to more diesel generator operation or more fossil fuel inputs at Dominion Energy instead of a faster shift to renewables.
Air quality is also part of the physical story. Natural-gas turbines release air pollutants at any scale, and diesel generators worsen the problem. Elon Musk previously violated air quality laws when he set up dozens of turbines to power a data center in Memphis, according to the Environmental Protection Agency. When public utilities build infrastructure of this magnitude, communities have traditionally expected a say in where it goes, while private companies are now undertaking projects on similar scale. Opposition also draws on fears of job losses, existential risks, concentrated corporate power and misinformation; most facilities use far less water than many people think. The debate also notes that enormous electricity use is not inherently bad, because many advances that improved modern life required it.
Latest: Power Purchases and Political Signals
Most AI data centers being built elsewhere are not designed to connect to the existing grid. Many new campuses are planned for rural areas with little grid infrastructure, so companies are installing natural-gas-powered turbines behind the meter, meaning self-generated onsite power, and building diesel generators for backup. Anthropic has reportedly agreed to pay $3.4 billion for gas turbines in what is described as the largest power generation purchase by an AI company.
Protests have led some companies to pursue deals that raise tax revenues, hire local workers and increase community involvement. Those deals do not remove the physical need for power plants, transmission lines and backup systems near homes.
The latest political signals were mixed. It is possible that newly elected politicians’ actual stances on data centers will not be as negative as the ones they campaigned on. But industry insiders see their ambitions constrained less by public opposition than by a lack of electricity.
If new data centers need onsite power, they may go where there are fewer people able to resist them. One option is the Permian Basin, where sparse populations and a network of natural-gas lines can make developer connections easier. Companies may also try projects abroad. Google announced the day after the elections that it will spend $15 billion on data center projects in Malaysia. Hours after midterms results came rolling in, Elon Musk posted that “Data centers in space looking pretty appealing right now.”
The current phase is defined by power capacity and physical consequences: grid rules in Virginia, gas turbine purchases for AI campuses, and a search for locations where electricity can be secured with fewer objections.