Data centers are adopting old jet engines as delays in securing power increase.

Chips & Infrastructure 0 views

AI data centers use converted jet engines for faster power as grid queues delay connections, but efficiency and emissions make this a short-term bridge.

Key Takeaways

  • AI data centers are using converted jet engines to generate power on site and bypass years-long grid connection delays.
  • Grid access can take about seven years for 100 megawatts in Northern Virginia, while jet-powered units can enable operation in around 24 months.
  • Companies including xAI, OpenAI, and Crusoe have adopted or ordered converted natural gas turbines from ProEnergy to accelerate AI campus buildouts.
  • The engines are less efficient and more polluting than conventional gas turbines, making them a short-term bridge rather than a permanent power solution.
  • Policy pressure and near-term power constraints are pushing operators toward self-generation, though environmental concerns may grow as the approach spreads.

Some AI data centers are bypassing years-long grid queues by generating electricity on site with converted jet engines, according to a Tuesday report by the New York Times. The trend shows how far power supply has fallen behind the AI buildout: grid connections can take years, while repurposed aircraft engines can help a facility start operating in about 24 months.

Background: Grid queues stall AI data centers

For years, developers of large AI campuses have faced long waits for two things: grid connections and new turbines. The core problem is electricity supply, not construction speed alone.

The timeline gap is stark. In Northern Virginia, hooking up 100 megawatts to the grid takes about seven years, according to the International Energy Agency. By comparison, Rystad Energy analyst Audun Martinsen told the Times that jet-powered units can help a data center be running in 24 months. “It’s all about getting power as fast as possible,” he said.

The delays are already costing operators business. Microsoft last month ended its role as anchor customer for Nscale’s data center in Loughton, England, after the local utility said sufficient power would not arrive until the early to mid-2030s. That shows how a utility timeline stretching into the next decade can cost a data center operator a major customer.

Development: xAI, OpenAI and Crusoe move to on-site turbines

xAI, the company led by Elon Musk, is among operators already using converted jet engines. The Times, citing state permits and satellite imagery, reported that xAI installed eight converted jet-engine turbines in Mississippi to support power for its Colossus 2 data center in Memphis.

ProEnergy supplies the units, rebuilding a GE engine commonly found on Boeing jets and converting it to burn natural gas. The engines are pulled from retired aircraft and are not anyone’s idea of a permanent power plant.

OpenAI moved in the same direction in 2025, adding gas turbines at its first Stargate site in Abilene, Texas. Crusoe, a Denver-based startup that builds AI data centers and is constructing the Abilene campus, ordered 13 converted ProEnergy units in April.

Not every turbine plan held. In September, Crusoe dropped a $1.25 billion plan to buy 29 natural gas turbines from Boom Supersonic, a company developing a supersonic passenger jet that has also begun selling a version of that engine as data center power. A Crusoe spokesperson told TechCrunch at the time that the company still plans to use turbines.

Latest: Self-generation pressure and short-term limits

The Trump administration is adding to the pressure by encouraging data centers to generate their own electricity.

The engines carry trade-offs. They are less efficient and more polluting than turbines built for conventional gas plants, and more units are needed to produce the same amount of power, the Times reported.

For now, speed is the main advantage. Most power capacity is expected to come on by 2031, a Mitsubishi Power executive told Bloomberg last week. Until then, converted jet engines may remain a bridge rather than a destination. Some experts say efficiency and environmental concerns may grow in importance in a year or two.

Meta Description: Converted jet engines from ProEnergy are helping xAI and other AI data centers get power faster, but grid delays and emissions keep them a short-term fix.

Tags: AI data centers, ProEnergy, xAI, OpenAI, power grid delays

Featured Image: Abstract data center turbine scene with natural gas infrastructure and power grid lines; no people, no logos, no text.