Anthropic joins AI's natural gas rush and purchases $3.4 billion worth of turbines.
Anthropic bought $3.4 billion in Caterpillar gas turbines, moving from renting AI compute to owning power amid grid delays and gas price risk.
Key Takeaways
- Anthropic is spending $3.4 billion on Caterpillar natural gas turbines capable of producing up to 1.7 gigawatts of electricity.
- The purchase marks a shift from Anthropic’s usual model of renting computing capacity, such as its $1.25 billion-per-month deal with xAI, toward owning power generation assets.
- The move is driven by the AI power crunch, including long backlogs for turbines and lengthy queues to connect to the electrical grid.
- Anthropic is part of a wider trend among AI companies, including Google, Amazon, Microsoft, and Meta, building on-site natural gas power for data centers.
- The reliance on natural gas exposes these companies to potential price spikes and could sharply increase U.S. natural gas consumption by data centers.
Meta description: Anthropic is spending $3.4 billion on Caterpillar natural gas turbines as the AI power crunch pushes it toward owning capacity rather than renting compute.
Tags: Anthropic, Caterpillar, AI infrastructure, natural gas, data centers
Featured image: Abstract visualization of natural gas turbines powering AI infrastructure, with glowing lines and industrial geometry, no people, logos, or text.
Anthropic natural gas turbines show how acute the AI power crunch has become. The company, which has generally avoided buying physical infrastructure, is spending $3.4 billion on Caterpillar generators, according to a Financial Times report. The purchase matters because it moves Anthropic away from its usual model of renting computing capacity and toward owning generation capacity.
A history of renting compute
Historically, Anthropic has preferred to rent rather than buy infrastructure. In its S-1 filing in May, the company disclosed that it is paying SpaceX subsidiary xAI $1.25 billion per month through May 2029 to use xAI's computing power. Anthropic stated, "We expect to enter into additional similar services contracts," signaling that it planned to keep expanding rented compute arrangements.
The company is also planning to go public this year. Its S-1 filing already disclosed the xAI arrangement.
How the turbine purchase unfolded
The $3.4 billion deal involves Caterpillar generators that equipment supplier OnePWR had originally ordered. Those generators are capable of producing up to 1.7 gigawatts of electricity, a measure of power capacity.
According to the report, OnePWR ordered the turbines a couple years ago but could not find financing to complete the purchase. Anthropic had planned to buy them from OnePWR, but instead went directly to Caterpillar, the manufacturer.
It is not clear why OnePWR could not secure financing despite Anthropic's apparent interest as a customer. The report suggests Anthropic likely wanted to keep the generating capacity to itself rather than give a competitor an opportunity to acquire it.
Why the power market forced a change
The power market uncertainty may have forced Anthropic's hand. The backlog for natural gas turbines stretches into the early 2030s, and queues to connect to the electrical grid can be just as long. As demand for compute ramps up, those delays make the market for power increasingly uncertain.
Anthropic's purchase therefore looks like a last resort. It shifts the company from renting compute to owning generators.
The wider AI gas buildout
Anthropic is not alone. AI companies have been increasing purchases of natural gas equipment and supplies in recent years. Google, Amazon, Microsoft, and Meta have all announced plans to build massive natural gas power plants to power their data centers on site, rather than drawing from the public grid.
That spending has given a second wind to fracking, the drilling method used to extract natural gas from underground rock. If the buildout proceeds as planned, U.S. data centers alone could consume more natural gas than Germany and Japan combined by 2035.
The reliance on natural gas also exposes large cloud and AI companies, often called hyperscalers, to price fluctuations. According to one analyst, prices could more than triple by the end of the decade in some markets. If that happens, Anthropic may face a serious case of buyer's remorse after choosing to own generation capacity instead of continuing to rent compute.