Crusoe sold its troubled Wyoming data center project to Google.
Crusoe sold its unfinished Wyoming data center to Google, which plans a $17 billion, 10-gigawatt buildout, highlighting AI infrastructure risks.
Key Takeaways
- Crusoe sold its unfinished southeastern Wyoming data center project to Google, transferring a site originally planned with Tallgrass to scale toward 10 gigawatts.
- Google plans to invest $17 billion in the Wyoming campus, after reportedly raising concerns about Crusoe’s cost and construction timeline.
- The deal highlights the execution risks facing independent AI infrastructure developers, including equipment shortages, power constraints, budgets, and local opposition.
- Crusoe’s broader AI-infrastructure business continues, with major projects for Oracle, OpenAI, Microsoft, Meta, and Jane Street, plus recent financing and board changes.
- The Wyoming takeover will test whether Google can convert the 10-gigawatt ambition into delivered capacity on a realistic schedule.

Crusoe's Wyoming data center project changed hands on Friday, when the eight-year-old Denver-based developer confirmed it had sold an unfinished data center project in southeastern Wyoming to Google. Bloomberg first reported the deal in June. The transaction hands Google a site that Crusoe had announced last year with Blackstone-backed infrastructure company Tallgrass, with plans to eventually scale it to 10 gigawatts of power capacity. It also shows how difficult it can be for independent data center developers to deliver massive projects on time and within budget, especially when equipment and power are hard to secure and local opposition can complicate development.
Background: From Mining Roots to AI Campus Ambitions
Crusoe was founded by Chase Lochmiller, now its CEO, and Cully Cavness as a cryptocurrency-mining business powered by natural gas that would otherwise have been burned off. It recently gained a valuation of $30.9 billion. Today, Crusoe earns revenue by leasing data center space to customers that bring their own GPUs, renting out its own GPUs, and selling compute power used to run AI models, known as inference.
The Wyoming project reflected that shift toward very large AI infrastructure. Crusoe's initial announcement last year set out a path toward 10 gigawatts of power capacity, a scale that depends on long construction schedules, equipment supply, and power arrangements.
Development: Google Raises Concerns, Then Takes Over
Google had been a target customer for the Wyoming project, but Crusoe tried and failed to land it. Google reportedly raised concerns about the cost and construction timeline under Crusoe's management. The company then took over development, though it did not disclose how much it paid Crusoe for the unfinished project. Instead, Google announced plans to invest $17 billion to develop the data center campus.
The sale did not sever Google's relationship with Crusoe. Crusoe is still developing another data center for Google near Amarillo, Texas. The Wyoming setback also did not stop Crusoe from raising money: in September, it raised a $3.9 billion round.
Latest: Other Large Projects Continue
Crusoe's largest projects serve some of the biggest names in AI. Its campus in Abilene, Texas, is being built in phases for Oracle and OpenAI. The company is also constructing a separate 900-megawatt campus next door for Microsoft, with its first building expected to come online in mid-2027. Meta is also a customer, and Bloomberg reported that trading firm Jane Street signed a $13 billion, five-year cloud deal with Crusoe.
The September financing also changed Crusoe's board. The company added three board members, including JB Straubel, the Redwood Materials founder and Tesla board member who invested in Crusoe in 2021. Crusoe later became the first customer of Straubel's energy-storage business.
Current Stage: Ownership Changes, Ambition Remains
At this stage, Google is responsible for a Wyoming campus that Crusoe could not advance under its original plan, while Crusoe keeps its Amarillo project and other AI-infrastructure contracts intact. The $17 billion investment and the 10-gigawatt ambition make the Wyoming site a test of whether the project's scale can match a realistic construction schedule. The next question is whether Google's takeover can turn a 10-gigawatt plan into delivered capacity under the $17 billion investment.
Meta description: Google takes over Crusoe's unfinished Wyoming data center and plans a $17 billion development, highlighting risks for independent AI infrastructure developers.
Tags: Crusoe, Google, Wyoming data center, AI infrastructure, GPU leasing
Comments
No comments yet. Be the first to comment.